Gibson Solar I — Project Summary

Queue ID
PJM-AF2-091
Capacity
34 MW
Technology
Solar
Status
active
Location
King George, VA
Region
PJM
Developer
IA Status
IA Executed

Gibson Solar I

BetaActiveSolarPJMLBNL + Live

34 MW generation in King George, VA · In queue since February 2020 · Proposed COD December 2027

34 MW

Capacity

1

Components

Solar

6y 1m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

7y 10m

Construction75%
Queue EntryFeb 7, 2020

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

VA

County

King George

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Oak Grove-Dahlgren 230 kV

Data Source

LBNL + Live

No news available for this project.