— Project Summary

Queue ID
PJM-AF2-088
Capacity
6.5 MW
Technology
Solar
Status
active
Location
Clearfield, PA
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveSolarPJMLBNL + Live

6.5 MW generation in Clearfield, PA · In queue since February 2020 · Proposed COD September 2026

6.5 MW

Capacity

1

Components

Solar

6y 1m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

6y 7m

Impact Study25%
Queue EntryFeb 5, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-09-01

Project Details

State

PA

County

Clearfield

Region

PJM

Developer

Utility

PENELEC

Entity

PJM

Point of Interconnection

Shawville-Clearfield 34.5 kV II

Data Source

LBNL + Live

No news available for this project.