BetaActiveSolarPJMLBNL
70 MW generation in Pitt, NC · In queue since January 2020 · Proposed COD June 2022
70 MW
Capacity
1
Components
Solar
6y 2m
In Queue
System Impact Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
2y 5m
Schedule
46 months past proposed COD
Impact Study25%
Queue EntryJan 31, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-06-30
Project Details
State
NC
County
Pitt
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Chinquapin-Everetts 230 kV
Data Source
LBNL