— Project Summary

Queue ID
PJM-AF2-069
Capacity
9.3 MW
Technology
Wind
Status
active
Location
Bureau, IL
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveWindPJMLBNL

9.3 MW generation in Bureau, IL · In queue since January 2020 · Proposed COD October 2021

9.3 MW

Capacity

1

Components

Wind

6y 2m

In Queue

System Impact Study

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

1y 9m

Schedule

54 months past proposed COD

Impact Study25%
Queue EntryJan 31, 2020

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-10-04

Project Details

State

IL

County

Bureau

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Crescent Ridge 138 kV

Data Source

LBNL

No news available for this project.