BetaActiveWindPJMLBNL
9.3 MW generation in Bureau, IL · In queue since January 2020 · Proposed COD October 2021
9.3 MW
Capacity
1
Components
Wind
6y 2m
In Queue
System Impact Study
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
1y 9m
Schedule
54 months past proposed COD
Impact Study25%
Queue EntryJan 31, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-10-04
Project Details
State
IL
County
Bureau
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Crescent Ridge 138 kV
Data Source
LBNL