150 MW generation in Blackford, IN · In queue since January 2020 · Proposed COD October 2022
150 MW
Capacity
1
Components
Solar
6y 2m
In Queue
System Impact Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
2y 9m
Schedule
42 months past proposed COD
Impact Study25%
Queue EntryJan 30, 2020
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-10-03
Project Details
State
IN
County
Blackford
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Jay 138 kV
Data Source
LBNL