— Project Summary

Queue ID
PJM-AF2-050
Capacity
50 MW
Technology
Solar
Status
active
Location
Cambria, PA
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveSolarPJMLBNL

50 MW generation in Cambria, PA · In queue since December 2019 · Proposed COD September 2021

50 MW

Capacity

1

Components

Solar

6y 3m

In Queue

System Impact Study

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

1y 9m

Schedule

56 months past proposed COD

Impact Study25%
Queue EntryDec 23, 2019

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-09-01

Project Details

State

PA

County

Cambria

Region

PJM

Developer

Utility

PENELEC

Entity

PJM

Point of Interconnection

Bearrock-Johnstown 230 kV

Data Source

LBNL

No news available for this project.