— Project Summary

Queue ID
PJM-AF2-046
Capacity
126 MW
Technology
Solar
Status
active
Location
Hertford, NC
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveSolarPJMLBNL

126 MW generation in Hertford, NC · In queue since December 2019 · Proposed COD June 2022

126 MW

Capacity

1

Components

Solar

6y 3m

In Queue

System Impact Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

2y 6m

Schedule

46 months past proposed COD

Impact Study25%
Queue EntryDec 19, 2019

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-06-01

Project Details

State

NC

County

Hertford

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Tunis-Mapleton 115 kV

Data Source

LBNL

No news available for this project.