BetaActiveSolarPJMLBNL
126 MW generation in Hertford, NC · In queue since December 2019 · Proposed COD June 2022
126 MW
Capacity
1
Components
Solar
6y 3m
In Queue
System Impact Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
2y 6m
Schedule
46 months past proposed COD
Impact Study25%
Queue EntryDec 19, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-06-01
Project Details
State
NC
County
Hertford
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Tunis-Mapleton 115 kV
Data Source
LBNL