500 MW generation in Halifax, VA · In queue since December 2019 · Proposed COD December 2022
500 MW
Capacity
1
Components
Solar
6y 3m
In Queue
System Impact Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
3 years
Schedule
39 months past proposed COD
Impact Study25%
Queue EntryDec 9, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-12-31
Project Details
State
VA
County
Halifax
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Clover-Rawlings 500 kV
Data Source
LBNL