BetaActiveSolarPJMLBNL + Live
13.5 MW generation in Clearfield, PA · In queue since November 2019 · Proposed COD September 2026
13.5 MW
Capacity
1
Components
Solar
6y 4m
In Queue
System Impact Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
6y 10m
Impact Study25%
Queue EntryNov 29, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-09-01
Project Details
State
PA
County
Clearfield
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Shawville-Clearfield 34.5 kV
Data Source
LBNL + Live
No news available for this project.