BetaActiveSolarPJMLBNL
72 MW generation in Hanover, VA · In queue since November 2019 · Proposed COD October 2023
72 MW
Capacity
1
Components
Solar
6y 4m
In Queue
System Impact Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 11m
Schedule
29 months past proposed COD
Impact Study25%
Queue EntryNov 27, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-10-27
Project Details
State
VA
County
Hanover
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
St. Johns 115 kV
Data Source
LBNL
No news available for this project.