Kincaid PV
20 MW generation in Christian, IL · In queue since October 2019 · Proposed COD December 2028
20 MW
Capacity
1
Components
Solar
6y 5m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
9y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-12-09
State
IL
County
Christian
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Kincaid 345 kV
Data Source
LBNL + Live
Vistra says ‘extraordinary leadership’ enabling Illinois’ transition away from coal
Vistra's large-scale battery storage project at Moss Landing, California, which repurposed a natural gas plant site. Image: Vistra Energy.
Vistra says ‘extraordinary leadership’ enabling Illinois’ transition away from coal
Vistra's large-scale battery storage project at Moss Landing, California, which repurposed a natural gas plant site. Image: Vistra Energy.
Vistra says ‘extraordinary leadership’ enabling Illinois’ transition away from coal
Vistra's large-scale battery storage project at Moss Landing, California, which repurposed a natural gas plant site. Image: Vistra Energy.
Vistra says ‘extraordinary leadership’ enabling Illinois’ transition away from coal
Vistra's large-scale battery storage project at Moss Landing, California, which repurposed a natural gas plant site. Image: Vistra Energy.
Last updated 2026-03-26