Missouri Avenue Battery Storage Project — Project Summary

Queue ID
PJM-AF2-025
Capacity
20 MW
Technology
Battery
Status
active
Location
Atlantic, NJ
Region
PJM
Developer
IA Status
Facility Study

Missouri Avenue Battery Storage Project

BetaActiveBatteryPJMLBNL

20 MW storage in Atlantic, NJ · In queue since November 2019 · Proposed COD April 2028

20 MW

Capacity

1

Components

Battery

6y 4m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

8y 5m

Facilities Study50%
Queue EntryNov 15, 2019

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-30

Project Details

State

NJ

County

Atlantic

Region

PJM

Developer

Utility

AEC

Entity

PJM

Point of Interconnection

Ontario 69 kV

Data Source

LBNL

No news available for this project.