Missouri Avenue Battery Storage Project
BetaActiveBatteryPJMLBNL
20 MW storage in Atlantic, NJ · In queue since November 2019 · Proposed COD April 2028
20 MW
Capacity
1
Components
Battery
6y 4m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
8y 5m
Facilities Study50%
Queue EntryNov 15, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-30
Project Details
State
NJ
County
Atlantic
Region
PJM
Developer
—
Utility
AEC
Entity
PJM
Point of Interconnection
Ontario 69 kV
Data Source
LBNL
No news available for this project.