Wild Grains Solar
BetaActiveSolarPJMLBNL + Live
150 MW generation in Van Wert, OH · In queue since October 2019 · Proposed COD December 2027
150 MW
Capacity
1
Components
Solar
6y 5m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
8y 2m
Construction75%
Queue EntryOct 18, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
OH
County
Van Wert
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Maddox Creek 345 kV
Data Source
LBNL + Live
No news available for this project.