100 MW storage in King George, VA · In queue since October 2019 · Proposed COD October 2029
100 MW
Capacity
1
Components
Battery
6y 5m
In Queue
Facility Study
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
10 years
Facilities Study50%
Queue EntryOct 15, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-10-01
Project Details
State
VA
County
King George
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Arnold's Corner-Dahlgren 230 kV
Data Source
LBNL + Live