West Lorain Power Plant 345 kV — Project Summary

Queue ID
PJM-AF2-004
Capacity
33 MW
Technology
Gas
Status
active
Location
Lorain, OH
Region
PJM
Developer
IA Status
IA Executed

West Lorain Power Plant 345 kV

BetaActiveGasPJMLBNL + Live

33 MW generation in Lorain, OH · In queue since October 2019 · Proposed COD June 2031

33 MW

Capacity

1

Components

Gas

6y 5m

In Queue

IA Executed

IA Status

COD target: 2031

Interconnection Timeline

Total Duration

11y 8m

Construction75%
Queue EntryOct 1, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2031-06-01

Project Details

State

OH

County

Lorain

Region

PJM

Developer

Utility

ATSI

Entity

PJM

Point of Interconnection

Beaver 345 kV

Data Source

LBNL + Live