West Lorain Power Plant 345 kV
BetaActiveGasPJMLBNL + Live
33 MW generation in Lorain, OH · In queue since October 2019 · Proposed COD June 2031
33 MW
Capacity
1
Components
Gas
6y 5m
In Queue
IA Executed
IA Status
COD target: 2031
Interconnection Timeline
Total Duration
11y 8m
Construction75%
Queue EntryOct 1, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2031-06-01
Project Details
State
OH
County
Lorain
Region
PJM
Developer
—
Utility
ATSI
Entity
PJM
Point of Interconnection
Beaver 345 kV
Data Source
LBNL + Live
No news available for this project.