SunEast Hooversville Solar
BetaSuspendedSolarPJMLBNL + Live
20 MW generation in Somerset, PA · In queue since October 2019 · Proposed COD August 2026
20 MW
Capacity
1
Components
Solar
6y 5m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
6y 10m
Suspended75%
Queue EntryOct 1, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-08-01
Project Details
State
PA
County
Somerset
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Hooversville 115 kV II
Data Source
LBNL + Live