BetaActiveSolarPJMLBNL + Live
20 MW generation in Ogle, IL · In queue since September 2019 · Proposed COD May 2028
20 MW
Capacity
1
Components
Solar
6y 6m
In Queue
System Impact Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
8y 8m
Impact Study25%
Queue EntrySep 30, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-05-27
Project Details
State
IL
County
Ogle
Region
PJM
Developer
—
Utility
ComEd
Entity
PJM
Point of Interconnection
Twombley Road
Data Source
LBNL + Live
No news available for this project.