— Project Summary

Queue ID
PJM-AF1-302
Capacity
42 MW
Technology
Solar
Status
active
Location
Jefferson, PA
Region
PJM
Developer
IA Status
IA Executed

BetaActiveSolarPJMLBNL + Live

42 MW generation in Jefferson, PA · In queue since September 2019 · Proposed COD December 2027

42 MW

Capacity

1

Components

Solar

6y 6m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

8y 3m

Construction75%
Queue EntrySep 30, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

PA

County

Jefferson

Region

PJM

Developer

Utility

PENELEC

Entity

PJM

Point of Interconnection

Brookville-Squab Hollow 138 kV

Data Source

LBNL + Live