BetaActiveSolarPJMLBNL + Live
42 MW generation in Jefferson, PA · In queue since September 2019 · Proposed COD December 2027
42 MW
Capacity
1
Components
Solar
6y 6m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
8y 3m
Construction75%
Queue EntrySep 30, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
PA
County
Jefferson
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Brookville-Squab Hollow 138 kV
Data Source
LBNL + Live
No news available for this project.