Chester Solar Technology Park — Project Summary

Queue ID
PJM-AF1-291
Capacity
20 MW
Technology
Solar
Status
active
Location
Chesterfield, VA
Region
PJM
Developer
IA Status
System Impact Study

Chester Solar Technology Park

BetaActiveSolarPJMLBNL + Live

20 MW generation in Chesterfield, VA · In queue since September 2019 · Proposed COD June 2027

20 MW

Capacity

1

Components

Solar

6y 6m

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

7y 9m

Impact Study25%
Queue EntrySep 30, 2019

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-06-30

Project Details

State

VA

County

Chesterfield

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Tyler 34.5 kV

Data Source

LBNL + Live

No news available for this project.