Scioto Solar — Project Summary

Queue ID
PJM-AF1-285
Capacity
100 MW
Technology
Solar+Battery
Status
active
Location
Hardin, OH
Region
PJM
Developer
IA Status
IA Executed

Scioto Solar

BetaActiveSolarBatteryPJMLBNL + Live

100 MW hybrid in Hardin, OH · In queue since October 2019 · Proposed COD December 2026

100 MW

Capacity

1

Components

Solar

6y 5m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

7y 2m

Construction75%
Queue EntryOct 2, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

OH

County

Hardin

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Gunn Road 345 kV

Data Source

LBNL + Live