— Project Summary

Queue ID
PJM-AF1-283
Capacity
130 MW
Technology
Solar
Status
active
Location
Highland, OH
Region
PJM
Developer
IA Status
Facility Study

BetaActiveSolarPJMLBNL + Live

130 MW generation in Highland, OH · In queue since September 2019 · Proposed COD May 2030

130 MW

Capacity

1

Components

Solar

6y 6m

In Queue

Facility Study

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

10y 8m

Facilities Study50%
Queue EntrySep 30, 2019

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-05-01

Project Details

State

OH

County

Highland

Region

PJM

Developer

Utility

Dayton

Entity

PJM

Point of Interconnection

Stuart-Clinton 345 kV

Data Source

LBNL + Live

No news available for this project.