— Project Summary

Queue ID
PJM-AF1-280
Capacity
200 MW
Technology
Solar
Status
active
Location
Lee, IL
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveSolarPJMLBNL

200 MW generation in Lee, IL · In queue since September 2019 · Proposed COD December 2022

200 MW

Capacity

1

Components

Solar

6y 6m

In Queue

System Impact Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

3y 3m

Schedule

40 months past proposed COD

Impact Study25%
Queue EntrySep 10, 2019

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-01

Project Details

State

IL

County

Lee

Region

PJM

Developer

Utility

ComEd

Entity

PJM

Point of Interconnection

Nelson-Lee County

Data Source

LBNL

No news available for this project.