15.75 MW generation in Armstrong, PA · In queue since September 2019 · Proposed COD July 2022
15.75 MW
Capacity
1
Components
Solar
6y 6m
In Queue
System Impact Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
2y 10m
Schedule
45 months past proposed COD
Impact Study25%
Queue EntrySep 30, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-07-01
Project Details
State
PA
County
Armstrong
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Timblin 34.5 kV
Data Source
LBNL