— Project Summary

Queue ID
PJM-AF1-240
Capacity
15.75 MW
Technology
Solar
Status
active
Location
Armstrong, PA
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveSolarPJMLBNL

15.75 MW generation in Armstrong, PA · In queue since September 2019 · Proposed COD July 2022

15.75 MW

Capacity

1

Components

Solar

6y 6m

In Queue

System Impact Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

2y 10m

Schedule

45 months past proposed COD

Impact Study25%
Queue EntrySep 30, 2019

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-07-01

Project Details

State

PA

County

Armstrong

Region

PJM

Developer

Utility

PENELEC

Entity

PJM

Point of Interconnection

Timblin 34.5 kV

Data Source

LBNL