50 MW storage in Cumberland, NJ · In queue since September 2019 · Proposed COD May 2023
50 MW
Capacity
1
Components
Battery
6y 6m
In Queue
System Impact Study
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 8m
Schedule
34 months past proposed COD
Impact Study25%
Queue EntrySep 28, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-05-31
Project Details
State
NJ
County
Cumberland
Region
PJM
Developer
—
Utility
AEC
Entity
PJM
Point of Interconnection
Sherman Ave - West Vineland 69 kV
Data Source
LBNL