AEUG Fleming Solar
BetaActiveSolarPJMLBNL
188.5 MW generation in Fleming, KY · In queue since September 2019 · Proposed COD May 2022
188.5 MW
Capacity
1
Components
Solar
6y 6m
In Queue
System Impact Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
2y 8m
Schedule
47 months past proposed COD
Impact Study25%
Queue EntrySep 27, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-05-31
Project Details
State
KY
County
Fleming
Region
PJM
Developer
—
Utility
EKPC
Entity
PJM
Point of Interconnection
Flemingsburg _x0013_ Spurlock 138kV
Data Source
LBNL