AEUG Fleming Solar — Project Summary

Queue ID
PJM-AF1-233
Capacity
188.5 MW
Technology
Solar
Status
active
Location
Fleming, KY
Region
PJM
Developer
IA Status
System Impact Study

AEUG Fleming Solar

BetaActiveSolarPJMLBNL

188.5 MW generation in Fleming, KY · In queue since September 2019 · Proposed COD May 2022

188.5 MW

Capacity

1

Components

Solar

6y 6m

In Queue

System Impact Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

2y 8m

Schedule

47 months past proposed COD

Impact Study25%
Queue EntrySep 27, 2019

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-05-31

Project Details

State

KY

County

Fleming

Region

PJM

Developer

Utility

EKPC

Entity

PJM

Point of Interconnection

Flemingsburg _x0013_ Spurlock 138kV

Data Source

LBNL