Cottontail Solar 7
BetaSuspendedSolarPJMLBNL + Live
35 MW generation in Columbia, PA · In queue since September 2019 · Proposed COD November 2028
35 MW
Capacity
1
Components
Solar
6y 6m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
9y 2m
Suspended75%
Queue EntrySep 28, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-11-30
Project Details
State
PA
County
Columbia
Region
PJM
Developer
—
Utility
PPL
Entity
PJM
Point of Interconnection
Bowmans Mill-Scott 69 kV
Data Source
LBNL + Live