— Project Summary

Queue ID
PJM-AF1-223
Capacity
150 MW
Technology
Solar
Status
active
Location
Jay, IN
Region
PJM
Developer
IA Status
Facility Study

BetaActiveSolarPJMLBNL + Live

150 MW generation in Jay, IN · In queue since September 2019 · Proposed COD December 2026

150 MW

Capacity

1

Components

Solar

6y 6m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

7y 3m

Facilities Study50%
Queue EntrySep 27, 2019

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

IN

County

Jay

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Keystone-Desoto 345 kV

Data Source

LBNL + Live

No news available for this project.