Hoosier Line Solar
BetaActiveSolarPJMLBNL + Live
180 MW generation in White, IN · In queue since September 2019 · Proposed COD September 2027
180 MW
Capacity
1
Components
Solar
6y 6m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
8 years
Facilities Study50%
Queue EntrySep 27, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-09-15
Project Details
State
IN
County
White
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Reynolds-Olive #1 345 kV
Data Source
LBNL + Live