Hoosier Line Solar — Project Summary

Queue ID
PJM-AF1-207
Capacity
180 MW
Technology
Solar
Status
active
Location
White, IN
Region
PJM
Developer
IA Status
Facility Study

Hoosier Line Solar

BetaActiveSolarPJMLBNL + Live

180 MW generation in White, IN · In queue since September 2019 · Proposed COD September 2027

180 MW

Capacity

1

Components

Solar

6y 6m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

8 years

Facilities Study50%
Queue EntrySep 27, 2019

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-15

Project Details

State

IN

County

White

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Reynolds-Olive #1 345 kV

Data Source

LBNL + Live

No news available for this project.