CG Fulton County
199 MW generation in Fulton, OH · In queue since September 2019 · Proposed COD May 2028
199 MW
Capacity
1
Components
Solar
6y 6m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
8y 8m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-05-31
State
OH
County
Fulton
Region
PJM
Developer
—
Utility
ATSI
Entity
PJM
Point of Interconnection
East Fayette 138 kV
Data Source
LBNL + Live
Ohio Power Siting Board Approves Ritter Station Solar Project Near Fayette In 7–2 Vote
By: Jacob Kessler THE VILLAGE REPORTER jacob@thevillagereporter.com. The Ohio Power Siting Board voted 7-2 at its 1:30 p.m. meeting on...
Fayette residents clash at hearing over proposed solar project impact
CG Fulton County has proposed a 1700-acre solar farm in Gorham Township, which would be connected by a 2.2-mile transmission line to the...
Last updated 2026-03-26