Henry County Solar
BetaSuspendedSolarPJMLBNL + Live
40 MW generation in Henry, OH · In queue since September 2019 · Proposed COD August 2026
40 MW
Capacity
1
Components
Solar
6y 6m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
6y 11m
Suspended75%
Queue EntrySep 27, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-08-01
Project Details
State
OH
County
Henry
Region
PJM
Developer
—
Utility
AMPT
Entity
PJM
Point of Interconnection
Napoleon Muni 138 kV
Data Source
LBNL + Live