— Project Summary

Queue ID
PJM-AF1-204
Capacity
255 MW
Technology
Wind
Status
active
Location
Vermillion, IN
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveWindPJMLBNL

255 MW generation in Vermillion, IN · In queue since September 2019 · Proposed COD December 2022

255 MW

Capacity

1

Components

Wind

6y 6m

In Queue

System Impact Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

3y 3m

Schedule

39 months past proposed COD

Impact Study25%
Queue EntrySep 25, 2019

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-12-31

Project Details

State

IN

County

Vermillion

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Eugene 345 kV

Data Source

LBNL

No news available for this project.