— Project Summary

Queue ID
PJM-AF1-176
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
St. Joseph, MI
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveSolarBatteryPJMLBNL

300 MW hybrid in St. Joseph, MI · In queue since September 2019 · Proposed COD October 2022

300 MW

Capacity

1

Components

Solar

6y 6m

In Queue

System Impact Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

3y 1m

Schedule

41 months past proposed COD

Impact Study25%
Queue EntrySep 25, 2019

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-10-31

Project Details

State

MI

County

St. Joseph

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Corey 138 kV

Data Source

LBNL