300 MW hybrid in St. Joseph, MI · In queue since September 2019 · Proposed COD October 2022
300 MW
Capacity
1
Components
Solar
6y 6m
In Queue
System Impact Study
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
3y 1m
Schedule
41 months past proposed COD
Impact Study25%
Queue EntrySep 25, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-10-31
Project Details
State
MI
County
St. Joseph
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Corey 138 kV
Data Source
LBNL