CL-Route 58 B — Project Summary

Queue ID
PJM-AF1-167
Capacity
13.515 MW
Technology
Solar
Status
suspended
Location
Clarion, PA
Region
PJM
Developer
IA Status
System Impact Study

CL-Route 58 B

BetaSuspendedSolarPJMLBNL + Live

13.515 MW generation in Clarion, PA · In queue since September 2019 · Proposed COD January 2026

13.515 MW

Capacity

1

Components

Solar

6y 6m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

6y 4m

Suspended25%
Queue EntrySep 24, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-01-31

Project Details

State

PA

County

Clarion

Region

PJM

Developer

Utility

APS

Entity

PJM

Point of Interconnection

West Freedom-C&K Coal 25 kV