BetaActiveBatteryPJMLBNL + Live
100 MW storage in Martin, KY · In queue since September 2019 · Proposed COD May 2028
100 MW
Capacity
1
Components
Battery
6y 6m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
8y 8m
Facilities Study50%
Queue EntrySep 20, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-05-31
Project Details
State
KY
County
Martin
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Inez 138 kV
Data Source
LBNL + Live
No news available for this project.