— Project Summary

Queue ID
PJM-AF1-161
Capacity
50 MW
Technology
Battery
Status
active
Location
Van Buren, MI
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveBatteryPJMLBNL

50 MW storage in Van Buren, MI · In queue since September 2019 · Proposed COD March 2022

50 MW

Capacity

1

Components

Battery

6y 6m

In Queue

System Impact Study

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

2y 6m

Schedule

50 months past proposed COD

Impact Study25%
Queue EntrySep 20, 2019

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2022-03-01

Project Details

State

MI

County

Van Buren

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Valley 138 kV

Data Source

LBNL

No news available for this project.