Chesterfield CT Units 3&4
BetaActiveGasPJMLBNL + Live
569 MW generation in Chesterfield, VA · In queue since September 2019 · Proposed COD December 2029
569 MW
Capacity
1
Components
Gas
6y 6m
In Queue
IA Executed
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
10y 3m
Construction75%
Queue EntrySep 18, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2029-12-31
Project Details
State
VA
County
Chesterfield
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Chesterfield 230 kV
Data Source
LBNL + Live
No news available for this project.