— Project Summary

Queue ID
PJM-AF1-124
Capacity
836 MW
Technology
Offshore Wind
Status
active
Location
City Of Chesapeake, VA
Region
PJM
Developer
IA Status
System Impact Study

BetaActiveOffshore WindPJMLBNL

836 MW generation in City Of Chesapeake, VA · In queue since September 2019 · Proposed COD December 2026

836 MW

Capacity

1

Components

Offshore Wind

6y 6m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

7y 3m

Impact Study25%
Queue EntrySep 17, 2019

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

VA

County

City Of Chesapeake

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Oceana 230 kV

Data Source

LBNL

No news available for this project.