Morrow County Solar II
BetaSuspendedSolarPJMLBNL + Live
64 MW generation in Morrow, OH · In queue since September 2019 · Proposed COD March 2026
64 MW
Capacity
1
Components
Solar
6y 6m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
6y 6m
Suspended75%
Queue EntrySep 17, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-03-31
Project Details
State
OH
County
Morrow
Region
PJM
Developer
—
Utility
ATSI
Entity
PJM
Point of Interconnection
Cardington-Liberty 69 kV
Data Source
LBNL + Live
No news available for this project.