Lake Trout Solar
BetaActiveSolarBatteryPJMLBNL + Live
200 MW hybrid in Blackford, IN · In queue since September 2019 · Proposed COD January 2028
200 MW
Capacity
1
Components
Solar
6y 6m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
8y 4m
Construction75%
Queue EntrySep 13, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2028-01-31
Project Details
State
IN
County
Blackford
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Keystone-Desoto 345 kV
Data Source
LBNL + Live
No news available for this project.