Wilson Solar — Project Summary

Queue ID
PJM-AF1-098
Capacity
80 MW
Technology
Solar
Status
active
Location
Erie, PA
Region
PJM
Developer
IA Status
IA Executed

Wilson Solar

BetaActiveSolarPJMLBNL + Live

80 MW generation in Erie, PA · In queue since August 2019 · Proposed COD January 2028

80 MW

Capacity

1

Components

Solar

6y 7m

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

8y 5m

Construction75%
Queue EntryAug 30, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-01-29

Project Details

State

PA

County

Erie

Region

PJM

Developer

Utility

PENELEC

Entity

PJM

Point of Interconnection

Four Mile Jct-Corry East 115 kV

Data Source

LBNL + Live

No news available for this project.