Jackson Center Solar II
BetaActiveSolarPJMLBNL + Live
20 MW generation in Mercer, PA · In queue since August 2019 · Proposed COD July 2026
20 MW
Capacity
1
Components
Solar
6y 7m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
6y 11m
Construction75%
Queue EntryAug 31, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-07-31
Project Details
State
PA
County
Mercer
Region
PJM
Developer
—
Utility
ATSI
Entity
PJM
Point of Interconnection
Henderson-Stoneboro 69 kV
Data Source
LBNL + Live
No news available for this project.