Sculpin Solar — Project Summary

Queue ID
PJM-AF1-091
Capacity
180 MW
Technology
Solar
Status
active
Location
Dekalb, IN
Region
PJM
Developer
IA Status
IA Executed

Sculpin Solar

BetaActiveSolarPJMLBNL + Live

180 MW generation in Dekalb, IN · In queue since August 2019 · Proposed COD November 2028

180 MW

Capacity

1

Components

Solar

6y 7m

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

9y 3m

Construction75%
Queue EntryAug 30, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-11-30

Project Details

State

IN

County

Dekalb

Region

PJM

Developer

Utility

AEP

Entity

PJM

Point of Interconnection

Varner - Sowers 138 kV

Data Source

LBNL + Live

No news available for this project.