Sculpin Solar
BetaActiveSolarPJMLBNL + Live
180 MW generation in Dekalb, IN · In queue since August 2019 · Proposed COD November 2028
180 MW
Capacity
1
Components
Solar
6y 7m
In Queue
IA Executed
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
9y 3m
Construction75%
Queue EntryAug 30, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2028-11-30
Project Details
State
IN
County
Dekalb
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Varner - Sowers 138 kV
Data Source
LBNL + Live
No news available for this project.