Rogue's Wind
BetaActiveWindPJMLBNL + Live
109.9 MW generation in Clearfield, PA · In queue since August 2019 · Proposed COD September 2026
109.9 MW
Capacity
1
Components
Wind
6y 7m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
7y 1m
Construction75%
Queue EntryAug 30, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-09-01
Project Details
State
PA
County
Clearfield
Region
PJM
Developer
—
Utility
PENELEC
Entity
PJM
Point of Interconnection
Madera-Westover South 115 kV