Flat Run Solar — Project Summary

Queue ID
PJM-AF1-083
Capacity
55 MW
Technology
Solar
Status
active
Location
Barren, KY
Region
PJM
Developer
IA Status
IA Executed

Flat Run Solar

BetaActiveSolarPJMLBNL + Live

55 MW generation in Barren, KY · In queue since August 2019 · Proposed COD December 2026

55 MW

Capacity

1

Components

Solar

6y 7m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

7y 4m

Construction75%
Queue EntryAug 31, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-12-15

Project Details

State

KY

County

Barren

Region

PJM

Developer

Utility

EKPC

Entity

PJM

Point of Interconnection

Green County-Saloma 161 kV

Data Source

LBNL + Live