18 MW generation in Preble, OH · In queue since August 2019 · Proposed COD April 2028
18 MW
Capacity
1
Components
Solar
6y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
8y 8m
Facilities Study50%
Queue EntryAug 13, 2019
Interconnection request submitted to ISO/RTO
System Impact StudyCurrent
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-01
Project Details
State
OH
County
Preble
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
College Corner 138 kV
Data Source
LBNL + Live
No news available for this project.