Cassius Blue Solar
BetaActiveSolarBatteryPJMLBNL + Live
94 MW hybrid in Sussex, VA · In queue since August 2019 · Proposed COD August 2031
94 MW
Capacity
1
Components
Solar
6y 7m
In Queue
IA Executed
IA Status
COD target: 2031
Interconnection Timeline
Total Duration
12 years
Construction75%
Queue EntryAug 9, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2031-08-01
Project Details
State
VA
County
Sussex
Region
PJM
Developer
—
Utility
Dominion
Entity
PJM
Point of Interconnection
Carson-Rogers Rd 500 kV
Data Source
LBNL + Live
No news available for this project.