Juliet Energy
BetaActiveSolarPJMLBNL + Live
50 MW generation in Wood, OH · In queue since July 2019 · Proposed COD May 2027
50 MW
Capacity
1
Components
Solar
6y 8m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 10m
Construction75%
Queue EntryJul 31, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-05-29
Project Details
State
OH
County
Wood
Region
PJM
Developer
—
Utility
ATSI
Entity
PJM
Point of Interconnection
Weston 69 kV
Data Source
LBNL + Live
No news available for this project.