Juliet Energy — Project Summary

Queue ID
PJM-AF1-064
Capacity
50 MW
Technology
Solar
Status
active
Location
Wood, OH
Region
PJM
Developer
IA Status
IA Executed

Juliet Energy

BetaActiveSolarPJMLBNL + Live

50 MW generation in Wood, OH · In queue since July 2019 · Proposed COD May 2027

50 MW

Capacity

1

Components

Solar

6y 8m

In Queue

IA Executed

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

7y 10m

Construction75%
Queue EntryJul 31, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-05-29

Project Details

State

OH

County

Wood

Region

PJM

Developer

Utility

ATSI

Entity

PJM

Point of Interconnection

Weston 69 kV

Data Source

LBNL + Live

No news available for this project.