Flint Grid
200 MW storage in Licking, OH · In queue since July 2019 · Proposed COD May 2027
200 MW
Capacity
1
Components
Battery
6y 8m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
7y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-05-01
State
OH
County
Licking
Region
PJM
Developer
—
Utility
AEP
Entity
PJM
Point of Interconnection
Jug Street 138 kV
Data Source
LBNL + Live
Ohio Power Siting Board gives approval for state’s first grid-scale battery storage project
The Ohio Power Siting Board has given approval to a large-scale standalone battery energy storage system (BESS) project for the first time in its history.
First OPSB-approved battery energy storage system
On October 20, 2022, the Ohio Power Siting Board (OPSB) issued a certificate of environmental compatibility and public need for the...
Ohio Power Siting Board denies solar project for first time
The Ohio Power Siting Board denied the application for Birch Solar, a proposed 300 MW solar farm in Allen and Auglaize counties,...
Ohio Power Siting Board denies solar project for first time
The Ohio Power Siting Board denied the application for Birch Solar, a proposed 300 MW solar farm in Allen and Auglaize counties,...
Last updated 2026-03-26