Horseshoe Bend Solar
BetaActiveSolarPJMLBNL + Live
60 MW generation in Green, KY · In queue since July 2019 · Proposed COD November 2026
60 MW
Capacity
1
Components
Solar
6y 8m
In Queue
IA Executed
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
7y 4m
Construction75%
Queue EntryJul 14, 2019
Interconnection request submitted to ISO/RTO
System Impact Study
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-11-30
Project Details
State
KY
County
Green
Region
PJM
Developer
—
Utility
EKPC
Entity
PJM
Point of Interconnection
Summer Shade - Green County 161 kV
Data Source
LBNL + Live
No news available for this project.