Prospect Power — Project Summary

Queue ID
PJM-AF1-028
Capacity
200 MW
Technology
Battery
Status
active
Location
Rockingham, VA
Region
PJM
Developer
IA Status
IA Executed

Prospect Power

BetaActiveBatteryPJMLBNL + Live

200 MW storage in Rockingham, VA · In queue since May 2019 · Proposed COD February 2026

200 MW

Capacity

1

Components

Battery

6y 10m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

6y 9m

Schedule

2 months past proposed COD

Construction75%
Queue EntryMay 13, 2019

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2026-02-01

Project Details

State

VA

County

Rockingham

Region

PJM

Developer

Utility

Dominion

Entity

PJM

Point of Interconnection

Endless Caverns 115 kV

Data Source

LBNL + Live